Operating for 35 Years I 150+ Years of Experience I 84,000+ Jobs Completed I Iso Accredited I In-house Engineering

Quick Enquiry Call Us

Search

If you cant find what you’re after please don’t hesitate to contact us.

Select Region

Please select the global region website you'd like to view.

Asia
Japan

Quick Enquiry

Submit your enquiry using our online form and include a brief message about the type of issues you are experiencing. One of the Mainmark experts will contact you as soon as possible.

Hidden
This field is for validation purposes and should be left unchanged.

Project Profile V16T140

Gas pipe decommissioned with Terefil®

Sub-industry
Utilities
Problems
Pipe Decommissioning
Location
ACT
Year
2016
Solutions
Void Filling
Technology
Teretek®

The problem

As part of the works to upgrade the tram service in Acland Street, St Kilda, a 95-year-old, low-pressure gas pipe running beneath the street needed to be safely decommissioned.

The 450mm, 390m long gas main needed to be relocated to facilitate improved tram stops along this busy road. The works were part of a broader program to revitalise the streetscape, led by the transport authorities and local council.

The terminus sits on one of Melbourne’s busiest tram routes and near the entrance to the iconic Luna Park. The project site occupied the southbound traffic lane on Acland Street and the tram track.

A time-efficient and cost-effective solution was required to minimise disruption. Mainmark was appointed by Comdain Infrastructure to fill the pipe with Terefil®, and ultimately reduced the project time from an estimated five days to just a single 12-hour shift.

The solution

The pipe needed to be decommissioned with minimum impact on the busy streetscape, completing the work as fast as possible to minimise traffic control costs, interruption to the tram network, and inconvenience to local residents and businesses.

The steel gas pipe had lead joints, which were unlikely to withstand pumping pressures greater than 150kPa. The project team was required to work within these parameters.

This eliminated the use of traditional sand-filled grouts as they would be too slow to place and could only be pumped approximately 100m into the pipe, requiring multiple access points and much greater disruption to this busy shopping strip.

The Result

Mainmark recommended its unique Terefil® solution. The advanced, lightweight structural fill material is ideal for when granular fills or aggregate materials are too heavy. It is highly-flowable and easily placed, making it well-suited to the project’s tight schedule and access limitations.

It also does not require pre-loading or compaction for settlement mitigation, and its specialised material performance properties, including zero bleed and typically less than 0.1%- 0.3% shrinkage, support safe and sustainable construction practices.

Mainmark placed Terefil® at 20m3 per hour from the low end of the pipe. Our team successfully placed 69m3 of Terefil® in just 4 hours to completely fill the 450mm, 390m long gas main.

By using Terefil®, Mainmark reduced the planned 10-day street closure to three days, which delivered significant cost savings in traffic control. The trams were able to resume full services a week earlier than originally anticipated.

Resources

Project Resources & Downloads

Gas Pipe Decommissioned With Terefil®
Terefil®
Next Project

Underground Gas Main Decommissioned with Terefil®

Mainmark

© 2024 The Mainmark group of companies. ‘Mainmark®’, ‘Terefil®’, ‘Terefirm®’ and ‘Teretek®’ are trademarks of the Mainmark group of companies.

Mainmark Ground Engineering Pty Ltd
ABN: 51 606 182 503

ISO 9001
ISO 14001
ISO 45001

Residential

Commercial

Infrastructure

Mining

About Mainmark

Our team

Careers

Contact

Technologies

Media & Press

News

Awards

Privacy Policy

Terms and Conditions

Created by Codex

YouTube
Facebook
LinkedIn
Instagram