Operating for 35 Years I 150+ Years of Experience I 84,000+ Jobs Completed I Iso Accredited I In-house Engineering

Quick Enquiry Call Us

Search

If you cant find what you’re after please don’t hesitate to contact us.

Select Region

Please select the global region website you'd like to view.

Asia
Japan

Quick Enquiry

Submit your enquiry using our online form and include a brief message about the type of issues you are experiencing. One of the Mainmark experts will contact you as soon as possible.

Hidden
This field is for validation purposes and should be left unchanged.

Project Profile N7057

Airport Runway Rehabilitation

Sub-industry
Airports
Problems
Out-of-level Concrete
Location
Japan
Year
2005
Solutions
Slab Lifting
Technology
Uretek®

The problem

10,000m2 of concrete runway and taxiway at Gimpo, South Korea’s number 2 airport, suffered from varying degrees of subsidence, from 50mm to 160mm. The subsidence meant that the surface design stormwater profiles were no longer effective. Ponding after rain created ice patches, which could cause aircraft to skid. The project was completed with precision in 28 days by Uretek Slab Lifting bringing the surfaces back to level, and Uretek Deep Injection effecting re-support where required.

The solution

To remove all areas of potential ponding from the entire airport pavement by raising the sunken slabs and restoring the hydraulic contours and to reestablish and re-confirm complete support back onto the sub-base soils. Very importantly the project was required to be achieved without any interruption to airport operations.

The Result

The Australian team was flown in with all technical equipment and materials.

From multiple Operations Rigs, expanding, structural resins were injected beneath the slabs to restore the hydraulic contours in subsided sections. Uretek Deep Injection was used to strengthen the foundation ground.

Unlike concrete ‘mud-jacking’, which had been trialled previously unsuccessfully, the Uretek resins achieved near maximum strength almost instantly and thus allowed aircraft to operate on injected areas just 30 minutes later.

The airport slabs were rehabilitated with ponding on the runways and taxiways eliminated completely. The surface contours were restored precisely, enabling aircraft to operate in smooth, problem-free conditions.

This extensive project was completed in just 28 days without interruption to airport operations at any time.

Resources

Project Resources & Downloads

Airport Runway Rehabilitation
Teretek®
Next Project

Sea Wall Void Filled and Sealed

Mainmark

© 2024 The Mainmark group of companies. ‘Mainmark®’, ‘Terefil®’, ‘Terefirm®’ and ‘Teretek®’ are trademarks of the Mainmark group of companies.

Mainmark Ground Engineering Pty Ltd
ABN: 51 606 182 503

ISO 9001
ISO 14001
ISO 45001

Residential

Commercial

Infrastructure

Mining

About Mainmark

Our team

Careers

Contact

Technologies

Media & Press

News

Awards

Privacy Policy

Terms and Conditions

Created by Codex

YouTube
Facebook
LinkedIn
Instagram