Get a FREE Quote Call Us

Search

If you cant find what you’re after please don’t hesitate to contact us.

Select Region

Please select the global region website you'd like to view.

Asia
Japan

Get a FREE Quote

Submit your enquiry using the online form with a brief description of the issue. A Mainmark expert will be in touch within 24–48 hours (excluding weekends and public holidays).

After clicking Submit, you’ll receive an email with the next steps—please check your inbox and spam folder.

Hidden
Photos or reports of issues (optional)
Drop files here or
Max. file size: 16 MB.
    Consent
    This field is for validation purposes and should be left unchanged.

    Project Profile W13L130

    Mine ROM Bridge Re-supported & Re-levelled

    Sub-industry
    Mining
    Problems
    Subsidence
    Location
    WA
    Year
    2013
    Solutions
    Ground Improvement
    Technology
    Uretek®

    The problem

    Latent ground conditions on an iron ore mine site in Western Australia caused the footings of a 600 tonne ROM sidetipper bridge to subside up to 530mm over a 130m2 area.

    Side-tipper trucks haul loads from the Run of Mine (ROM) stocks and they dump their loads from an overhead bridge at the top of the ROM pad. This feeds the crusher located below. Our team successfully re-supported the bridge, consolidated the foundation ground raised the bridge approach footings and re-levelled the structure back to very close to its design levels.

    This was achieved without hampering the production output rate of the mine and without the need for demolition or open excavation. The bridge was corrected in twelve working days. This was done safely: without incident or any disruption.

    Aerial view of Run-Of-Mine pad and the side-tipper bridge.

    The solution

    A key objective was to raise the structure as near as possible to the original design levels, whilst also taking into consideration the surrounding structural elements some of which had also subsided. The other key objective was to strengthen the foundation ground of the bridge as much as possible.

    A major aspect of this brief was to devise a method of working without hampering the production rate of the Mine, which depended on a continuous flow of trucks delivering their payloads from the bridge and at the base of the bridge.

     

    Centre Section Of The Bridge Before And After Rectification

    The Result

    Mainmark worked with the design engineers and chose the specialised resin for its highly compressive tensile strength and water-displacing properties.

    First Inspection Test Plan and Construction Risk Assessment Workshop was designed to allow our crew to work safely under the bridge and behind rigid barriers. Then geotechnical investigation, including DCP testing, was undertaken to determine the weak sub-grade zones.

    For the Uretek Deep-Injection process, injection tubes were installed to various depths, ranging from directly below the footings to approximately 6m below ground.

    The liquid resins injected through very small diameter tubes followed the path of least resistance (weak soils and voids). The chemical expansion of the resins densified the substrate soil until the force required to compact further was equal to the force required to lift the weight of the ROM bridge structure.

    Continuing the injection, the upward pressure of the expanding resins began to gradually lift the structure with a lifting pressure of up to 400kPa.

    The need to avoid placing strain onto the surrounding structural elements meant that no particular element of the bridge could be lifted more than a few mm at a time. Every injection point (at approx 50 locations across the site) had to be injected not just once but dozens of times.

     

    Injection of resin simultaneously at 4 points.

    One element raised in relation to the adjacent one.

    Footing movement was carefully monitored by a number of locally placed laser levels and slab level gauges. Settlement was not uniform across the site nor even across a single section of footing, eg there was 140mm discrepancy across an 8 lineal meter section. So to ensure that the structure was not subjected to unnecessary strain, lift was limited to 40mm per phase of injection (typical injection area covered 8m2).

    Once the majority of lift was completed, the structure was loaded with additional weight directly over the injection zone. This ensured that soil was compacted enough to support the weight of the structure and the loads that would be imposed on it. The bridge structure was raised to within ± 4mm of the required levels. Bearing capacity of the soils was substantially improved in all areas treated (by 330% on average). In some locations it was increased by 550%. Maximum lift recorded was approximately 530mm and no area failed to be raised to desired levels. Total material injected was 30tonnes: the equivalent of the volume of 50 large concrete trucks being placed under the bridge, all delivered through 16mm tubing.

    Resources

    Project Resources & Downloads

    Mine ROM Bridge Re-supported & Re-levelled
    Teretek®
    Next Project

    ROM Bridge Embankment Rehabilitated

    Mainmark

    © 2026 The Mainmark group of companies. ‘Mainmark®’, ‘Terefil®’, ‘Terefirm®’ and ‘Teretek®’ are trademarks of the Mainmark group of companies.

    Mainmark Ground Engineering Pty Ltd
    ABN: 51 606 182 503

    ISO 9001
    ISO 14001
    ISO 45001

    Solutions

    Ground Improvement

    Subsidence Repair

    Re-Levelling

    Void Filling

    Slab Lifting

    Crack Wall Repair

    Sinking Floors

    Sinking Foundation Repair

    Underpinning Repairs

    Locations

    Adelaide

    Brisbane

    Canberra

    Hobart

    Melbourne

    New South Wales

    Perth

    Queensland

    South Australia

    Sydney

    Tasmania

    Townsville

    Victoria

    Western Australia

    Sectors

    Commercial

    Residential

    Infrastructure

    Mining

    Technologies

    Teretek®

    Terefil®

    JOG

    About Us

    Our team

    Careers

    Media & Press

    News

    Awards

    Contact

    Locations
    Mainmark Sydney

    Level 7/124 Walker Street, North Sydney NSW 2060

     

    Mainmark Melbourne

    Unit 8, 33 Rosalie Street, Springvale VIC 3171

    Mainmark South Australia

    19 Heath St, Lonsdale SA 5160

    Mainmark Queensland

    20 Computer Road, Yatala QLD 4207

    Mainmark Perth

    115 Excellence Dr, Wangara WA 6065

    Mainmark Tasmania

     4/11 McRorie Court Cambridge TAS 7170

    Privacy Policy

    Terms and Conditions

    Created by Codex

    YouTube
    Facebook
    LinkedIn
    Instagram