Problem
A concrete reservoir was experiencing significant voiding and uneven settlement beneath its ring beam and floor slab. Mainmark delivered a targeted resin injection solution to fill the voids, re-establish ground contact, and stabilise the foundation without excavation or interrupting operations.
A concrete water reservoir, supported by a ring beam foundation and concrete floor slab, began exhibiting uneven settlement across its perimeter. Approximately 30% of the ring beam had subsided by up to 50 mm due to significant voiding beneath the foundation. Ongoing erosion and natural ground settlement had created cavities under sections of the structure, resulting in loss of ground contact and uneven bearing support. This differential movement posed a risk to the reservoir’s structural integrity and long-term serviceability. The council required a fast, non-invasive remediation method to re-establish uniform foundation support without excavation or prolonged interruption to reservoir operations.
Solution
Mainmark proposed a targeted polyurethane resin injection solution to fill the voids and re-support both the affected sections of the ring beam and the internal floor slab.
The works involved incremental injection beneath the ring beam to depths of up to 2,500 mm below ground level (BGL), allowing the expanding structural resin to penetrate and densify multiple soil layers. This process reinstated contact between the ring beam, floor slab, and subgrade while compacting and stabilising the underlying soil matrix. The internal slab was similarly treated using controlled resin injection to restore uniform support and eliminate voiding beneath the floor area. All works were performed using small-diameter injection points, enabling precise control of lift and ground improvement while maintaining reservoir operation throughout. The process was completed without excavation, noise, or contamination risk, meeting the council’s operational and environmental requirements.
Result
The incremental injection program successfully restored full bearing support beneath the affected 30% of the ring beam and supporting the internal floor slab, eliminating voids and reinstating uniform support across the structure.
Post-treatment monitoring confirmed effective ground densification, stable load transfer, and improved foundation integrity.
The works were completed efficiently, safely, and without operational downtime, delivering a durable, non-disruptive, and cost-effective solution that safeguarded the reservoir’s long-term performance.
Resources
Project Resources & Downloads
Re-Supporting a Subsiding Reservoir with Targeted Resin Injection
Download file
Please fill out this form to access this file.Need help?
Need help with a project? Contact us today.
© 2025 The Mainmark group of companies. ‘Mainmark®’, ‘Terefil®’, ‘Terefirm®’ and ‘Teretek®’ are trademarks of the Mainmark group of companies.
Mainmark Ground Engineering Pty Ltd
ABN: 51 606 182 503