Project Profile N3289

Wartime Explosives Magazine Re-supported

Sub-industry
Public Buildings
Problems
Subsidence
Location
NSW
Year
2003
Solutions
Re-levelling
Technology
Uretek®

The problem

Located in a National Park, on the banks of Sydney’s Middle Harbour, the old, wartime explosives magazine had fallen into disrepair and was especially in need of major footing re-levelling and foundation compaction to maintain its safety.

As there was no access to the site by road, a Mainmark self contained operations unit was brought in by barge and the footings of the building were completely re-levelling and re-supported.

The solution

The overall objective was to return the building footings to a level, safe and stable condition. The specific objectives were: firstly to raise and relevel the structure to within 10mm of its assumed design levels; and secondly to compact and improve the bearing capacity of the wall footings and so minimise the potential for further settlement of any poorly compacted soils.

The Result

With subsidence of up to 70mm evident in some locations, the foundation ground of the entire Wartime Explosives Magazine Re-supported N3289 80m2 area of the building was injected with Uretek expanding structural resin. The 180mm thick reinforced concrete floor slabs were raised, correcting several areas of dishing and re-levelling the whole floor area.

To compact and strengthen the wall foundations, and to return the walls to plumb, Uretek Deep-Injection was applied beneath 20 lineal metres of the wall footing beams. Constant monitoring and control ensured the correct amount of lifting and compaction during both processes.

The foundations of the building were returned to a stable condition with level floors and plumb, resupported walls.

Resources

Project Resources & Downloads

Wartime Explosives Magazine Re Supported
Next Project

Harbour Seawall Rehabilitated

© 2023 The Mainmark group of companies. ‘Mainmark®’, ‘Terefil®’, ‘Terefirm®’ and ‘Teretek®’ are trademarks of the Mainmark group of companies.

Mainmark Ground Engineering Pty Ltd
ABN: 51 606 182 503

Residential

Commercial

Infrastructure

Mining

About Mainmark

Our team

Careers

Contact

Technologies

Media & Press

News

Awards

Privacy Policy

Terms and Conditions

Created by Codex