Operating for 35 Years I 150+ Years of Experience I 84,000+ Jobs Completed I Iso Accredited I In-house Engineering

Quick Enquiry Call Us

Search

If you cant find what you’re after please don’t hesitate to contact us.

Select Region

Please select the global region website you'd like to view.

Asia
Japan

Quick Enquiry

Submit your enquiry using our online form and include a brief message about the type of issues you are experiencing. One of the Mainmark experts will contact you as soon as possible.

Hidden
This field is for validation purposes and should be left unchanged.

Project Profile N12V008

Void Fill On Brick Arch

Sub-industry
Rail
Problems
Erosion
Location
QLD
Year
2011
Solutions
Void Filling
Technology
Other

The problem

Redbank Tunnel, located along the Main Southern Railway, a brick-lined “horseshoe” tunnel, was reconsolidated. The tunnel is 314m in length. Brick was used for railway tunnels until the 1930s, when the pouring of concrete on-site was introduced. The tunnel is approximately 6.3m height and 8.3m width. The brick arch is 470mm thick, with handpacked backfill above and beside against rock. Through the tunnel, the double track consists of welded rails on concrete sleepers.

The solution

The first objective was to grout fissures in the rock above the brick arch. We were required to work above a 3m height line, working from the soffit of the brick arch. The second objective was to bind potentially loose rock sections together and reduce water ingress and erosion on this historic rail tunnel.

The Result

There had been concern for the tunnel due to mine subsidence in the area. Prior ground radar investigation suggested a volume of voids in the range from 30m2 to 50m2 , along a section of the tunnel roof 20m long and located towards the northern end of the tunnel. The methodology was to void fill to approximately 500mm above the arch, working at approximately 2-3m centres, over an area of approximately 260m2 of tunnel roof. Two pump lines and two Operations Crews were required. The work was executed over a weekend during a routine track shut-down. The tunnel had to be operational on Monday, on time, and this project was achieved without delay or complication.

Resources

Project Resources & Downloads

Void Fill On Brick Arch
Next Project

Restoring Culverts In A Rainforest Area

Mainmark

© 2024 The Mainmark group of companies. ‘Mainmark®’, ‘Terefil®’, ‘Terefirm®’ and ‘Teretek®’ are trademarks of the Mainmark group of companies.

Mainmark Ground Engineering Pty Ltd
ABN: 51 606 182 503

ISO 9001
ISO 14001
ISO 45001

Residential

Commercial

Infrastructure

Mining

About Mainmark

Our team

Careers

Contact

Technologies

Media & Press

News

Awards

Privacy Policy

Terms and Conditions

Created by Codex

YouTube
Facebook
LinkedIn
Instagram