The problem
Three culverts located in a high rainfall rainforest area in Far North Queensland were requiring correction. Our method was by far the most cost-effective way to fix the problems, as the alternative of closing the roads and replacing the culverts would have been far too costly. Key issues were not to cause any impact on the pristine environment, to ensure road support, while causing the least possible interruption to traffic.
The solution
Sealing and re-align the culverts to ensure their correct operation and re-supporting the road without environmental impact.
The Result
Working inside the slippery, wet pipes, our team correctly re-aligned the culverts, sealed the joints and filled 10m3 of voids. The culverts were re-aligned and re-supported. The roadway was re-supported. No material escaped into the environment.
Resources
Project Resources & Downloads
Restoring Culverts In A Rainforest Area
Permeation Grouting
Download file
Please fill out this form to access this file.Next Project
South Perth Seawall Rehabilitation
© 2023 The Mainmark group of companies. ‘Mainmark®’, ‘Terefil®’, ‘Terefirm®’ and ‘Teretek®’ are trademarks of the Mainmark group of companies.
Mainmark Ground Engineering Pty Ltd
ABN: 51 606 182 503