Operating for 35 Years I 150+ Years of Experience I 84,000+ Jobs Completed I Iso Accredited I In-house Engineering

Quick Enquiry Call Us

Search

If you cant find what you’re after please don’t hesitate to contact us.

Select Region

Please select the global region website you'd like to view.

Asia
Japan

Quick Enquiry

Submit your enquiry using our online form and include a brief message about the type of issues you are experiencing. One of the Mainmark experts will contact you as soon as possible.

Hidden
This field is for validation purposes and should be left unchanged.

Project Profile Q15N282

Stacker Crane Rail Re-levelled

Sub-industry
Mining
Problems
Subsidence
Location
QLD
Year
2015
Solutions
Re-levelling
Technology
Uretek®

The problem

Crane access to the coal stocks was limited by subsidence of one of the rail footing beams running down either side of the coal stack.

The giant stacker gantry crane rail was one kilometre in length. Crane access to the coal stocks was limited by subsidence of one of the rail footing beams running down either side of the coal stack. Mainmark treated the areas of subsidence, by injecting Uretek expanding structural resin under the rail beam. The beam was re-supported and lifted back to level, so that the client regained access to the entire coal stock.

The solution

The objective was to re-level the crane rail by re-supporting and re-levelling the concrete beam supporting it.

The Result

The reinforced concrete beams were one metre thick and three metres wide and had been built on general fill material, approx. eight metres deep. Prior to the construction of the rail beam, areas of the non-homogeneous fill material had been identified, removed and replaced. In the 21 months since construction of the beam, more settlement issues had arisen. Excessive deflection of the rail beam had developed under load. The joint between two slab sections had undergone settlement of 81 millimetres.

Geotechnical investigation via DCP and seismic testing indicated soft spots in the ground from two metres to six metres deep. Commissioned by the site engineers, Mainmark treated a section approximately 15 metres either side of the slab joint. Expanding structural resin was injected under the rail beam at depths of 2.5, 3.5 and 4.5 metres, as had been determined by pneumatic DCP tests. Injections were made through the centre of the rail beam, at either edge of the three metre wide beam and at one metre centres along the beam.

The beam was lifted back to level; and with several passes of the stacker crane, full support was shown to have been re-established.

Testing also indicated another area of soft ground at the start of the rail line. The slab beam there was 1.5 metres thick and was showing some signs of minor deflection. Very soft ground was found between 2.5 and 4.5 metres down, so structural resin was injected to compact and strengthen that area as well. On completion of the project by Mainmark, the client regained complete access to the significant stock of export coal.

Resources

Project Resources & Downloads

Stacker Crane Rail Re Levelled
Next Project

Terefil® Used to Abandon Pipeline at Iron Mine

Mainmark

© 2024 The Mainmark group of companies. ‘Mainmark®’, ‘Terefil®’, ‘Terefirm®’ and ‘Teretek®’ are trademarks of the Mainmark group of companies.

Mainmark Ground Engineering Pty Ltd
ABN: 51 606 182 503

ISO 9001
ISO 14001
ISO 45001

Residential

Commercial

Infrastructure

Mining

About Mainmark

Our team

Careers

Contact

Technologies

Media & Press

News

Awards

Privacy Policy

Terms and Conditions

Created by Codex

YouTube
Facebook
LinkedIn
Instagram