Operating for 35 Years I 150+ Years of Experience I 84,000+ Jobs Completed I Iso Accredited I In-house Engineering

Quick Enquiry Call Us

Search

If you cant find what you’re after please don’t hesitate to contact us.

Select Region

Please select the global region website you'd like to view.

Asia
Japan

Quick Enquiry

Submit your enquiry using our online form and include a brief message about the type of issues you are experiencing. One of the Mainmark experts will contact you as soon as possible.

Hidden
This field is for validation purposes and should be left unchanged.

Project Profile Q15M152

Jack-Assisted Driveway Slab Remediation

Sub-industry
Factories & Warehouses
Problems
Out-of-level Concrete
Location
QLD
Year
2015
Solutions
Slab Lifting
Technology
Uretek®

The problem

An external concrete driveway slab with deep edge beams had settled approximately 30mm and had moved 100mm out of its horizontal position.

19m of edge beam and 76m2 of slab required level correction. Mainmark applied a combination of bottle jacks placed atop bored piers and Uretek resin injections between the piers, to effect the re-levelling and re-support. A turnbuckle system aided the horizontal correction. A completely satisfactory remediation was achieved in nine hours.

The solution

The objectives were to raise and return the slab to its design levels, to re-support it and to move the slab horizontally back to its original position.

The Result

During the lifting of the edge beam by the jacks, Uretek resin was injected from above, to fill the void created and to re-support the slab a large amount of fill material had been washed out.

Six bored piers were placed under the edge beam at 3.6m centres. The spacings had been determined by the client’s project engineer based on the strength of the edge beam. The bored piers were stopped short 320mm below the underside of the edge beam. Six 20 tonne capacity bottle jacks were placed between the bored piers and the underside of the edge beam. The bottle jacks were used to lift the beam 30mm at the southern end and 6 to 10mm at the northern end.

During the lifting of the edge beam by the jacks, Uretek resin was injected from above, to fill the void created and to re-support the slab.

The lifting operation brought the slab back horizontally 85mm. Then a turnbuckle system fabricated by the client’s builder pulled it back the final 15mm. Once the required levels were achieved, metal posts and metal packers were placed between the edge beam and the bored piers. The jacks were retrieved and the jacking slots filled with high strength, nonshrink grout.

The required lift was achieved and the slab was resupported and returned to the required position vertically and horizontally. The client, engineer, local council and builder were all very pleased with the result.

Resources

Project Resources & Downloads

Jack-Assisted Driveway Slab Remediation
Next Project

JOG Corrects Slab Dishing in Large Transport Yard

Mainmark

© 2024 The Mainmark group of companies. ‘Mainmark®’, ‘Terefil®’, ‘Terefirm®’ and ‘Teretek®’ are trademarks of the Mainmark group of companies.

Mainmark Ground Engineering Pty Ltd
ABN: 51 606 182 503

ISO 9001
ISO 14001
ISO 45001

Residential

Commercial

Infrastructure

Mining

About Mainmark

Our team

Careers

Contact

Technologies

Media & Press

News

Awards

Privacy Policy

Terms and Conditions

Created by Codex

YouTube
Facebook
LinkedIn
Instagram