Sub-industry
Office Building
Problems
Earthquake Remediation
Location
Christchurch, NZ
Year
2014
Solutions
Ground Improvement
Technology
Deep Injection, JOG Computer-Controlled Grouting
Large Building Re-levelled by JOG & UDI
Summary
This two-storey commercial building with a footprint of 510m² had walls built of precast tilt-panels and had suffered significant earthquake subsidence.
In three weeks, Mainmark rectified the settlement, by applying JOG integrated computer grouting and injections of Uretek expanding structural resins.
Objectives
To raise and re-level the building precisely. It was essential to avoid any disturbance to the neighbouring building which was only 200mm from the rear wall.
Solution
Uretek Deep-injection was then undertaken to fill any voids in the foundations and to ensure full support for the floor slabs. Injections were made to a depth of 4,000mm; this part of the project taking 16 days, partly overlapping with the JOG work. The project was completely successful. The building was raised and re-levelled to the client’s complete satisfaction. There was no disturbance to the neighbouring building.
Resources
Download a pdf version of this project here
Large Building Re-levelled by JOG & UDI
Download file
Please fill out this form to access this file.Next Project
Large Christchurch House Re-levelled by JOG
© 2024 The Mainmark group of companies. ‘Mainmark®’, ‘Terefil®’, ‘Terefirm®’ and ‘Teretek®’ are trademarks of the Mainmark group of companies.
Mainmark Ground Engineering (NZ) Ltd